Ridgeford OperationsContact

Count the wait before the order is placed.

Supplier lead time starts after several internal decisions may already have happened. A useful purchasing review keeps those periods separate.

Reconstruct a small set of recent purchases.

Use the request, approval, purchase order and receipt information already available. For each purchase, establish when the need became clear, when a complete request reached purchasing, when it was approved and when the supplier confirmed the order.

Do not fill a missing timestamp with an estimate presented as fact. Mark it as unknown and ask the person who handled that part of the purchase. The absence of a record may itself explain why people have different accounts of the delay.

Distinguish the causes.

Incomplete request
Purchasing is waiting for a specification, quantity or other information needed to place the order.
Approval queue
The request is ready, but the person authorized to approve it has not acted or a substitute has not been defined.
Supplier commitment
The order has been placed, but the delivery date, quantity or other condition still needs confirmation.
Receipt and release
The goods have arrived but are not yet available for the operation that needs them.

Change the part of the route that explains the delay.

A supplier follow-up list will not fix an approval that waits for a weekly meeting. An additional approver will not resolve an incomplete specification. Choose a change that addresses the observed cause, then follow another purchase through the revised route.

Keep the check simple enough that purchasing and the requesting department can maintain it together.

Purchasing review · Back to the notes